As evidence of our ability to provide mechanical and electrical services in all segments, we have handled projects, both local and international, as shown below:
Year | Description & Service | Client: | |
---|---|---|---|
2023 | Project: | PLTA Cirata | Client: PT. PLN Cirata |
Service: | Retrovit LV MCC Unit 2 | ||
2023 | Project: | Stasiun Pompa Ancol | Client: PT. Epacs Sakti |
Service: | MV Panel Test | ||
2023 | Project: | Asahan | Client: PT Voith Hydro Indonesia |
Service: | SF6 Treatment | ||
2023 | Project: | 500kV Peranap | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 500kV String Set & HV Apparatus Cleaning and Maintenance | ||
2023 | Project: | Sulut 1 | Client: PT. Pembangunan Perumahan |
Service: | RCP Testing Commissioning | ||
2023 | Project: | Labrador Project - Singapore | Client: Toshiba Technical Services International Coporation |
Service: | GIT Installation | ||
2023 | Project: | Jakarta | Client: PT Innomotics Motors & Solutions |
Service: | HV Electric Motor Inspection | ||
2023 | Project: | Timor 1 | Client: PT. Siemens Energy Indonesia |
Service: | Relay Testing Commissioning | ||
2023 | Project: | PLTA Cirata | Client: PT. PLN Cirata |
Service: | TailRace Panel Replacement | ||
2023 | Project: | KUTAI Kerta Negara | Client: PT. ABB Sakti Industri |
Service: | RCP Testing Commissioning | ||
2023 | Project: | Nusantara Regas 1 - Floating Tank | Client: PT. Perusahaan Pelayaran Equinox |
Service: | Thermographic Inspection | ||
2023 | Project: | PT. Freeport Indonesia | Client: PT. Siemens Indonesia |
Service: | 8DB Installation and Testing | ||
2023 | Project: | Tabalong | Client: PT. Trakon |
Service: | Generator Testing | ||
2023 | Project: | PT. Pertamina Geothermal Energy Tbk - Kamojang | Client: PT. Pertamina Geothermal Energy Tbk |
Service: | 150kV CT Trouble Shooting | ||
2023 | Project: | RAPP Pekanbaru | Client: PT. Siemens Indonesia |
Service: | Busduct Installation | ||
2023 | Project: | Pertamina Balikpapan | Client: Pertamina Balikpapan |
Service: | Pengadaan TMC 5 Ton | ||
2023 | Project: | HEPP Rajamandala | Client: PT. Rajamandala |
Service: | Medium Voltage Switchgear Trouble Shooting | ||
2023 | Project: | PLTA Peusangan - Aceh | Client: PT. Andritz Hydro |
Service: | Generator and Trafo Testing | ||
2023 | Project: | CFSPP Timor 1 | Client: IKPT |
Service: | Generator Testing | ||
2023 | Project: | 500kV AIS Lengkong | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 500kV CVT Replacement | ||
2023 | Project: | PLTA Peusangan - Aceh | Client: PT. Andritz Hydro |
Service: | DC Battery Test | ||
2023 | Project: | PLTA Peusangan - Aceh | Client: PT. Andritz Hydro |
Service: | LV Switchgear Testing Commissiong | ||
2023 | Project: | Jakarta | Client: PT. Syntek Otomasi Indonesia |
Service: | Relay Micro 1000 A Test | ||
2023 | Project: | PLTS - Likupang | Client: |
Service: | PLTS Likupang Maintenance | PT. Syntek Otomasi Indonesia | |
2023 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | Voltage Transducer Replacement | ||
2023 | Project: | Chamsir IRAN | Client: Voith Hydro Austria |
Service: | Governer Commissioning | ||
2023 | Project: | EXXON Mobil Cepu | Client: EXXON Mobil Cepu |
Service: | Relay Protection and Switchgear Setting | ||
2023 | Project: | PLTU Sulut 1 | Client: PT. GT Ladang Teknik |
Service: | LV Panel Testing Commissioning | ||
2023 | Project: | Jakarta | Client: PT. ATOZ TEKNIK SEJAHTERA |
Service: | Ario Bimo - Testing and Commissioning | ||
2023 | Project: | PHE Jambi Merang | Client: PHE Jambi Merang |
Service: | SEPAM Setting | ||
2023 | Project: | Grand Inga Dam II Project - Congo | Client: PT. Voith Hydro Austria |
Service: | BOPE Installation and Commissioning | ||
2023 | Project: | 150kV GIS DAYEUH KOLOT | Client: PT MITRA PURNAMA ENGINEERING |
Service: | DC Battery Test | ||
2023 | Project: | ASAHAN | Client: PT Voith Hydro Indonesia |
Service: | Generator Test | ||
2023 | Project: | PLTU Vung Ang - Vietnam | Client: PT. Sulzer Indonesia |
Service: | Generator Test | ||
2023 | Project: | Jakarta | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | FAT Test RCP - Rengat | ||
2023 | Project: | PLTA Peusangan - Aceh | Client: PT. Andritz Hydro |
Service: | Unit 2 HIPOT Test | ||
2023 | Project: | Nusantara Regas 1 - Floating Tank | Client: Perusahaan Pelayaran Equinox ,PT |
Service: | HV Switchboard Service | ||
2023 | Project: | 150kV GIS Tambak Lorok | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 150kV GIS DS Dismentling Reinstallation and Testing | ||
2023 | Project: | 500kV AIS Bandung Selatan | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 500kV Corona Ring Repair | ||
2023 | Project: | Istana Negara - Jakarta | Client: PT. Siemens Indonesia |
Service: | 8DB Gas Filling and Testing | ||
2023 | Project: | PLTA Asahan | Client: PT Voith Hydro Indonesia |
Service: | Siemens T300 Testing Commissioning | ||
2022 | Project: | HM Sampoerna - Surabaya | Client: PT. Syntek Otomasi Indonesia |
Service: | MV Panel Test | ||
2022 | Project: | PLTA Asahan | Client: PT. WASA MITRA ENGINEERING |
Service: | Startor Core Test | ||
2022 | Project: | PLTA Peusangan - Aceh | Client: PT. Andritz Hydro |
Service: | Generator Testing | ||
2022 | Project: | 150kV AIS Krapyak | Client: PT Berca Buana Sakti |
Service: | GI KRAPYAK Reconfiguration | ||
2022 | Project: | 500kV AIS Peranap | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 500kV HV Apparatus Cleaning and Maintenance | ||
2022 | Project: | 500kV AIS Lengkong | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 500kV CVT Test | ||
2022 | Project: | PLTMG BIMA | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | Point to Point Test | ||
2022 | Project: | 70kV AIS Rumbai | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | Installation Testing and Commissioning | ||
2022 | Project: | 500kV AIS Lengkong | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | Hotspot Issue Closing | ||
2022 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | Tariff Meter Replacement | ||
2022 | Project: | 500kV AIS Indramayu | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | Hotspot Issue Closing | ||
2022 | Project: | PLTA Soedirman - MRICA | Client: PT. Sulzer Indonesia |
Service: | Generator Testing Commissioning | ||
2022 | Project: | PT CHANDRA ASRI - CILEGON | Client: PT. KRAKATAU DAYA LISTRIK |
Service: | MV Switchgear and Commissioning | ||
2022 | Project: | ADARO | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | Commissioning GI ADARO | ||
2022 | Project: | PLTA TOMASA | Client: PT. ARKORA HYDRO |
Service: | Maintenance PLTMH | ||
2022 | Project: | HEPP LAOS | Client: PT. Voith Hydro Shanghai Ltd |
Service: | HEPP Commissioning | ||
2022 | Project: | Nusantara Regas 1 - Floating Tank | Client: Perusahaan Pelayaran Equinox ,PT |
Service: | Generator Trouble Shooting | ||
2022 | Project: | PETROCHINA - TANJUNG JABUNG | Client: PT. Sulzer Indonesia |
Service: | Tubine and Generator Testing and Commissioning | ||
2022 | Project: | ENI Offshore - Sepinggan Balik Papan | Client: PT Bhumi Phala Perkasa |
Service: | Relay Test | ||
2022 | Project: | 500kV AIS Peranap | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | 500kV Shunt Reactor Installation Testing Commissioning | ||
2022 | Project: | 500kV AIS Bandung Selatan | Client: Hitachi Sakti Energy Indonesia ,PT |
Service: | Hotspot Issue Closing | ||
2022 | Project: | PLTA Renun | Client: PT. Sulzer Indonesia |
Service: | Turbine and Generator maintenance | ||
2022 | Project: | Agincourt MARTABE | Client: PT. SCHNEIDER ELECTRIC |
Service: | Ring Master Testing and Commissioning | ||
2022 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | Client: PT. TPSC ENGINEERING INDONESIA |
Service: | ACDB Voltage Transducer Replacement | ||
2022 | Project: | 150kV GIS Tambak Lorok | Client: HITACHI ABB Power Grids |
Service: | 150kV GIS and EM SOGI - Installation & Testing Commissioning | ||
2022 | Project: | Togo - Africa | Client: Voith Hydro GmbH & Co. KG |
Service: | installation and Testing Generator Tranformer 150 kV / 16 kV 33 MVA | ||
2021 | Project: | HEPP LAOS | Client: PT. Voith Hydro Shanghai Ltd |
Service: | HEPP Commissioning | ||
2021 | Project: | Bridgestone Factory - Karawang | Client: PT. Cahaya Indah Utama Sejahtera |
Service: | LV - MV SWG Preventif Maintenance | ||
2021 | Project: | 500kV AIS Indramayu | Client: PT. ABB Sakti Industri |
Service: | 500kV Stability Test | ||
2021 | Project: | PLTGU - Muara Tawar | Client: PT. ABB Sakti Industri |
Service: | Relay Modification Testing and Commissioning | ||
2021 | Project: | PLTMG - LUWUK | Client: PT. KRAKATAU DAYA LISTRIK |
Service: | DC Battery Test | ||
2021 | Project: | 500kV Indramayu | Client: PT. SCHNEIDER ELECTRIC |
Service: | 500kV CB & DS Testing | ||
2021 | Project: | AIS 500kV | Client: PT. ABB Sakti Industri |
Service: | 500kV SSVT Installation and Testing | ||
2021 | Project: | 500kV Indramayu | Client: PT MULTIFAB |
Service: | 500kV DS dismantling, Reinstall and Testing | ||
2021 | Project: | PLTA POSO | Client: PT. VOITH SHANGHAI |
Service: | Relay Commissioning | ||
2021 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | Intertrip Pemalang Batang | ||
2021 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | FRC & DCDB Relay Testing and Commissioning | ||
2021 | Project: | HEPP WANJI - KENYA | Client: PT. Voith Hydro Heidenheim |
Service: | BOPE Installation and Commissioning | ||
2021 | Project: | PLTU PAITON | Client: PT. POMI |
Service: | GSUT Unit 8 Maintenance | ||
2021 | Project: | PLTU Cirebon | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | BCT Test | ||
2021 | Project: | GI BARRU - SULSEL | Client: PT. TPSC ENGINEERING INDONESIA |
Service: | Commissioning Support | ||
2021 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | Client: PT. TOSHIBA ASIA PASIFIC INDONESIA |
Service: | DC Battery Test | ||
2021 | Project: | PLTU Cirebon | Client: PT. WASA MITRA ENGINEERING |
Service: | Contact Resistant | ||
2021 | Project: | PLTA Renun | Client: PT. ANDRITZ HYDRO |
Service: | HIPOT Test | ||
2021 | Project: | 150kV Kamojang - PT. Pertamina Geothermal Energy Tbk | Client: PT. ABB Sakti Industri |
Service: | Relay Replacement Testing and Commisioning | ||
2021 | Project: | GIS 150kV Mangga Besar | Client: PT. ABB Sakti Industri |
Service: | CB TEST MANGGA BESAR | ||
2021 | Project: | PLN - GIS 150kV Tambak Lorok | Client: PT ABB Sakti Industri |
Service: | 150kV GIS and EM SOGI - Installation & Testing Commissioning | ||
2020 | Project: | Cirebon 2, 1x1000 MW Coal Fired Steam Power Plant Project | PT. Toshiba Asia Pacific Indonesia |
Service: | Scope of Supply: Rental Test Equipment | ||
2020 | Project: | Indramayu 500KV Subtation, Erection & Installation | HITACHI ABB Power Grids |
Service: | Erection , Installation & Individual Testing | ||
2020 | Project: | Peranap 500KV Subtation, Erection & Installation | PT ABB Sakti Industri |
Service: | Erection , Installation & Individual Testing | ||
2019 | Project: | Supply Equipment tester | CV. Sinergy Indo Pratama |
Service: | Supply of KOCOS Promet - Contact Resistance test | ||
2019 | Project: | Supply Equipment tester | PT. Satyamitra Surya Perkasa |
Service: | Supply of KOCOS Promet - Contact Resistance test | ||
2019 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | PT. Toshiba Asia Pacific Indonesia |
Service: | Pre-Commissioning of GIS 500KV | ||
2019 | Project: | CFSPP 2x1000MW Tanjung Jati B Expansion, Jepara | PT. Toshiba Asia Pacific Indonesia |
Service: | SF6 Testing service of DILO Economic series machine, Analizer testing, Equipment testing of Transformer 60MVA and Votano CT 500kV | ||
2019 | Project: | HEPP 1x48 MW Rajamandala, Bandung | Nippa Tech CO,Ltd |
Service: | Generator Mechanical Supervisor Service | ||
2019 | Project: | Semangka HPP 2x28 MW, Lampung | Voith Hydro Indonesia |
Service: | HV Tesing - Electrical Equipment testing | ||
2019 | Project: | PLN - GIS+GIL 150kV Suvarna Sutra | PT. Siemens Indonesia |
Service: | GIS/GIL 150kV - Electrical System Testing & Commissioning | ||
2019 | Project: | GI Cikarang and Pertamina Plaju RU III | PT. ABB Sakti Industri |
Service: | Installation of Mechanical-Electrical retrofit Relay at CRP Panels | ||
2019 | Project: | GIS Ketapang | PT. ABB Sakti Industri |
Service: | Overhoul of Maintenace GIS Ketapang | ||
2019 | Project: | 5 PLN Gardu Induk area substation Project | PT. Graha Usaha Teknik |
Service: | Rental Equipment service of DILO Economic series machine | ||
2018 - 2019 | Project: | LRT Jakpro, Kelapa Gading | PT. Len Industri ( Persero ) |
Service: | Splicing & Testing FO Cable , Supply Material and service work | ||
2018 - 2019 | Project: | Mount Coffe Hydro Power 4x13MW, Liberia | Voith Hydro Liberia |
Service: | Service Charge Erction and Commissioning Hydroelectric Power Project | ||
2018 - 2019 | Project: | Hydro power plant Lamtakong 250MW, Thailand | Voith Hydro Shanghai Ltd |
Service: | Deputation of generator and electricsl balance of plant installation and commisioning | ||
2018 - 2019 | Project: | PLTP 80MW Geothermal Muara Laboh, Supreme Energy | PT. ABB Sakti Industri |
Service: | Erection/Installation & Commisioning work of 150kV Switchyard | ||
2018 - 2019 | Project: | HPP 1x48 MW Rajamandala, Bandung | Hyundai Engineering & Construction Co.,Ltd |
Service: | Electrical System testing & Commissioning | ||
2018 - 2019 | Project: | 11 PLN Gardu Induk area substation Project | PT. ABB Sakti Industri |
Service: | HSE - Safety Officer service for Gardu Induk site Project | ||
2018 - 2019 | Project: | 29 substation PLN Gardu Induk at Sumatra, Jawa & Kalimantan | PT. ABB Sakti Industri |
Service: | Electrical System testing & Commissioning | ||
2018 | Project: | 11 substation system for PLN Gardu Induk | PT. ABB Sakti Industri |
Service: | Electrical System testing & Commissioning at Factory for FAT | ||
2018 | Project: | PLN Gardu Induk Takengon & Bireun, Aceh | PT. ABB Sakti Industri |
Service: | Elecrical-Mechanical Maintenace service of Gardu Induk 150kV | ||
2018 | Project: | Seadrill USA | Sevan Drilling Nort America LLC |
Service: | Service for Reactivation Sevan Lousiana | ||
2018 | Project: | 5 PLN Gardu Induk area substation Project | PT. Graha Usaha Teknik |
Service: | Splicing & Testing FO Cable service | ||
2018 | Project: | PLN TJBTB project, 8 site warehouse PLN | PT. Siemens Indonesia |
Service: | Individual Testing CT, CVT, DS 70kV and 150kV at Warehouse PLN | ||
2018 | Project: | PLN - GI Padang & Payakumbuh Project | PT. Siemens Indonesia |
Service: | Electrical System Testing & Commissioning with Intertripping | ||
2018 | Project: | PLN Gardu Induk Begawan & Martapura | PT. Siemens Indonesia |
Service: | Inspection and Testing CT, CVT 70/150 kV | ||
2018 | Project: | RAPP Pertamina Plaju | PT. Siemens Indonesia |
Service: | Maintenace MV panel service, Electrical System Testing & Commissioning | ||
2018 | Project: | Apartment Kempinski | PT. Siemens Indonesia |
Service: | Preventive Maintenace Trafo Building | ||
2018 | Project: | GI Bantaeng & GIS Tambun | PT. Siemens Indonesia |
Service: | Relay testing, Electrical System Testing & Commissioning | ||
2018 | Project: | Sulfindo Merak Project | PT. Siemens Indonesia |
Service: | SF6 Gas filling, Analizer and Testing | ||
2018 | Project: | Sulfindo Merak Project | PT. Sulfindo Adiusaha |
Service: | SF6 Gas filling, Analizer Testing, and CPC 100 rental equipment | ||
2018 | Project: | Indocement Factory, Cibinong | PT. Eksakta Sinergi Indonesia |
Service: | MV Switcgear service, Electrical system Testing & Commisioning | ||
2017 - 2018 | Project: | Sucofindo Bengkulu Project | PT. Sucofindo |
Service: | Switcgear service & Testing at Bengkulu | ||
2017 - 2018 | Project: | HPP Victoria Dam, Srilanka | Voith Hydro GmnG & Co.KG |
Service: | Service Charge for Documentation and Storage/ Material at Sri langka Project Victoria | ||
2017 - 2018 | Project: | Semangka HPP 2x28 MW, Lampung | Voith Hydro Private Limited |
Service: | SF6 Testing Analizer DILO series and Electrical System testing & Commissioning | ||
2017 - 2018 | Project: | Sarulla Project | Hyundai Engineering & Construction Co.,Ltd |
Service: | Electrical System testing & Commissioning | ||
2017 - 2018 | Project: | PLN - GI 275kV & 150kV Wotu | PT. Siemens Indonesia |
Service: | Gardu Induk - Electrical System Testing & Commissioning | ||
2017 | Project: | Ingula Pumped Storage 4x270 MW, South of Africa | Voith Hydro GmnG & Co.KG |
Service: | Service Charge Commissioning Hydroelectric Power Project | ||
2017 | Project: | Exxson Mobile - Alsthom Singapore | Voltech Singapore Pte.Ltd |
Service: | Rental Equipment service of Omicron CMC 356 secondary injection with Higher End Differential Protection | ||
2017 | Project: | PLN - GI Cikupa Project | PT. ABB Sakti Industri |
Service: | Commissoning engineer service with Equipment Tools | ||
2017 | Project: | GI Lubuk Linggau Bangko Project | PT. ABB Sakti Industri |
Service: | Testing Equipment service with Operator | ||
2017 | Project: | SOGI Package 4 - at solo | PT. ABB Sakti Industri |
Service: | HSE - Safety Officer service for Gardu Induk site Project | ||
2017 | Project: | PLN - GI SOLO Project | PT. ABB Sakti Industri |
Service: | Retrofit CRP Panels - SOGI and Relays | ||
2017 | Project: | PLN - GI 150kV Duri Kosambi Project | PT. Siemens Indonesia |
Service: | Electrical System testing & Commissioning | ||
2017 | Project: | Indorama-Purwakarta Project | PT. Siemens Indonesia |
Service: | LV/MV Switcgear Maintenace service, Mechanical Electrical Testing | ||
2017 | Project: | Jangkrik Karimun | PT. Siemens Indonesia |
Service: | LV/MV Switcgear, Mechanical Electrical Testing & Commisioning | ||
2017 | Project: | Indarung Project - Semen Padang | PT. Siemens Indonesia |
Service: | Electrical System Testing & Commissioning | ||
2017 | Project: | Rental Equpment for 15 Location project | PT. Schneider Indonesia |
Service: | Rental service of : FFTK, DLRO, Ecofit ACB, MIT2302, Fluke354, CPC100, Hipot AC 50kV | ||
2017 | Project: | PLTH Karaha Bodas Tasik | PT. Schneider Indonesia |
Service: | Electrical System Testing service | ||
2017 | Project: | FAT GCP Panels Project | PT. Schneider Indonesia |
Service: | FAT service for Testing of GCP Panels | ||
2017 | Project: | GI Tanjung Uncang-Batam | PT. Schneider Indonesia |
Service: | Individual Testing service of Curent Transformer 70kV | ||
2017 | Project: | Cilegon Project | PT. Schneider Indonesia |
Service: | Relay Testing Service | ||
2017 | Project: | BRIDGESTONE Karawang | PT. Cahaya Indah Utama Sejahtera |
Service: | Nissin Switchgear Maintenance service | ||
2017 | Project: | Gajah Tunggal Project | PT. ABB Sakti Industri |
Service: | Electric Panel Wiring & Installation | ||
2017 | Project: | PLTU Kupang Project | PT. Santosa Makmur Sejahtera Energy |
Service: | LV/MV Switchgear, electrical System Testing & Commissioning | ||
2017 | Project: | Mandiri Dinamika Sejahtera | PT. Mandiri Dinamika Sejahtera |
Service: | Electrical System Testing | ||
2017 | Project: | Libra Dwi Kartika | PT. Libra Dwi Kartika |
Service: | Tangen Delta Testing | ||
2017 | Project: | PHE WMO Project | PT. Fedsin Rekayasa Pratama |
Service: | LV Switchgear Modification at KES Platform | ||
2017 | Project: | Testing 4- MW TG Package for Sugar Company Dumai | PT. Putri Utami Dumai |
Service: | Testing Relay | ||
2017 | Project: | Site work PLTU Lintas Rengat Riau | Siemens Indonesia & Singapore |
Service: | Testing and Commissioning for Floating Production Unit (FPU) for the Jangkrik Complex Project development | ||
2017 | Project: | Project:Sugar Factory at Dumai | Joint Operation with ISGEC as Main Contractor |
Service: | Tesing Generator Relay Panel, Transformer, LASCPT, HT Board 6,6KV at Dumai | ||
2016 | Project: | Site work PLTU Lintas Rengat Riau | PT. PITIBO DELYKARYA & ABB |
Service: | Testing and commissioning Trafo | ||
2016 | Project: | Jangkrik Project, South Korea | Siemens Indonesia & Singapore |
Service: | HULL ESSENTIAL LV/MV Switchgear Mechanical-Electrical Testing and commissioning | ||
2015 - 2016 | Project: | GI Pantai Indah Kapuk | PT. Siemens Indonesia |
Service: | Testing and commissioning for 150kV GIS system consist of 4 line Bys, 2 Transformer Bays and 1 Coupler Bay and Relay Control | ||
2015 - 2017 | Project: | Mount Coffe Hydro Power 4x13 MW, Liberia | Voith Hydro Gmbh &Co.KG |
Service: | Erection and Commissioning Hydroelectric Power Project | ||
2015 - 2017 | Project: | Ingula Pumped Storage 4x270 MW, South of Africa | Voith Hydro Gmbh &Co.KG |
Service: | Erection and Commissioning Hydroelectric Power Project | ||
2015 | Project: | Wampu HPP 3x15 MW, Medan | Voith Hydro Gmbh &Co.KG |
Service: | Supervisory Specialists for Commissioning Consultancy | ||
2015 | Project: | CFPP 2X30 MW PT. Antam Pomala | PT. Schneider Electric |
Service: | Commissioning Electrical system | ||
2015 | Project: | PT Semacom Integrated | PT. Semacom Integrated |
Service: | Sevice: Testing simoprime | ||
2015 | Project: | Siemens-Kepodang Project, Batam | Cooperation with PT. Graha Usaha Teknik |
Service: | Sevice: Commissioning Siprotec Relay and Funcionality of switchgear | ||
2015 | Project: | PLTU Payton Unit#7 | PT. Benfort Dwiputra Sinergi |
Service: | Fiber Optic Splicing and Testing | ||
2015 | Project: | PT. Freeport Indonesia, Papua Barat | PT. Freeport Indonesia |
Service: | Testing of Fiber Optic Cable Over DMLZ EBB to Acis Sub | ||
2015 | Project: | HEP Baghilar Stage II, India | Voith Hydro Pvt Ltd A-20&21, India |
Service: | Erection of the generators at Baghilar Hydroelectric Power Project | ||
2015 | Project: | Siemens LTD Korea Semiring Songa. | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning for DSME Semiring Songa Project. | ||
2015 | Project: | BI Building Jakarta | PT. Schneider Electric |
Service: | Tangen Delta Testing for Transformer in BI Building Jakarta | ||
2015 | Project: | Cong Thanh Cement Plant Thanh Hoa Province-Tinh Gia | PT. Siemens Ltd, Vietnam |
Service: | Commissioning for LV MCC package CTC | ||
2015 | Project: | ITP Cibinong Project | PT. Schneider Electric |
Service: | Commissioning Electrical system for ITP Cibinong P2 Project | ||
2015 | Project: | HEP Baghilar Stage II, India | Voith Hydro Gmbh &Co.KG |
Service: | Erection of the generators at Baghilar Hydroelectric Power Project | ||
2015 | Project: | BI Building Jakarta | PT. Schneider Electric |
Service: | Tangen Delta Testing for Transformer in BI Building Jakarta | ||
2014 | Project: | Bank Indonesia | PT. Schneider Electric |
Service: | Tan Delta test For transformer Test | ||
2014 | Project: | PT. Schneider Indonesia | PT. Schneider Electric |
Service: | Testing Electrical system | ||
2014 | Project: | PT. Schneider Indonesia | PT. Schneider Electric |
Service: | Installation Communication MV & LV Panel | ||
2014 | Project: | Siemens LTD Korea Semiring Songa. | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning for DSME Semiring Songa Project. | ||
2014 | Project: | Cement Mill in Dumai Clinker | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning Cement Mill in Dumai Clinker | ||
2014 | Project: | PLTU Kaban Agung Lahat Palembang | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning PLTU Kaban Agung Lahat Palembang Project | ||
2014 | Project: | PT. Pertamina-Talisman Jambi Merang | PT. Pertamina-Talisman Jambi Merang |
Service: | MV/LV Switchgear Maintenance And Protective Relay Calibration | ||
2014 | Project: | IKPP UPS Project | PT. Siemens Indonesia |
Service: | Commissioning for IKPP UPS Project | ||
2014 | Project: | Siemens_Ltd-SONGA Project | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning Electrical system | ||
2014 | Project: | Loesche_Comm Dumai Clinker Project | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning for Cement Mill Equipment | ||
2014 | Project: | Pelindo Il Project | PT. Siemens Indonesia |
Service: | instalasi and commissioning of In Class and Onsite Training for MV SWG 8DB10 for Pelindo Il Project | ||
2014 | Project: | PT. Schneider Indonesia_Project Musim Mas Medan | PT. Schneider Electric |
Service: | Injection 3 Phase Project Musim Mas Medan | ||
2014 | Project: | PT. Profelaute Sistem Indonesia | PT. Profelaute Sistem Indonesia |
Service: | Testing Sepam Protection Relay | ||
2014 | Project: | PT. ABB_Test a & Comm PLTU KalTim Project | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning and testing CB 150 Kv | ||
2014 | Project: | Freeport Project | PT. Siemens Indonesia |
Service: | Assembly Transformer | ||
2014 | Project: | Out-of-Pit Crushing and Conveying System | PT. FLSmidth Indonesia |
Service: | Commissioning and testing | ||
2014 | Project: | HEP Baghilar Stage II, India | Voith Hydro Gmbh &Co.KG |
Service: | Erection of the generators at Baghilar Hydroelectric Power Project | ||
2014 | Project: | Engury Project in Georgia | Voith Hydro Gmbh &Co.KG |
Service: | Commissioning in Engury Project in Georgia | ||
2014 | Project: | PTSI_Major Outage Muara Tawar 2014 | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning PTSI_Major Outage Muara Tawar 2014 | ||
2014 | Project: | Gunanusa-Yadana Project | Cooperation with PT. Graha Usaha Teknik |
Service: | HIPOT Testing | ||
2014 | Project: | ITP Cibinong Project | PT. Schneider Electric |
Service: | Commissioning Electrical system for ITP Cibinong P2 Project | ||
2014 | Project: | ITP P10 Marshalling | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2014 | Project: | PT. Freeport Indonesia, Papua Barat | PT. Freeport Indonesia |
Service: | Testing of Fiber Optic System For Acis Amole, Sub C South and PPC West | ||
2014 | Project: | PT. Kanger Consolidated Industries | PT. Kanger Consolidated Industries |
Service: | Commissioning for setting Protection Relay Siemens | ||
2014 | Project: | Hydro power Plant in Burundi | Voith Hydro Gmbh &Co.KG |
Service: | Installation Hydro power Plant in Burundi | ||
2014 | Project: | PT Technical South East Asia | PT. Technical South East Asia |
Service: | Fiber Optic Splicing and Testing | ||
2014 | Project: | PT Asia Pacific Fibers, Karawang | PT. Asia Pacific Fibers, Karawang |
Service: | Testing and servicing of protection relays of Asia Pacific Fiber.Complex by secondary injection | ||
2013 | Project: | PT Freeport Indonesia | PT. Siemens Indonesia |
Service: | Investigation of GIS 115kV | ||
2013 | Project: | PT Ozone Food Center Pantai INDAH Kapuk | PT. Pusaka Jaya Luhur Abadi |
Service: | Installation & Electrical System | ||
2013 | Project: | PT Global Solution Engineering | PT. Global Solution Engineering |
Service: | Splicing and Testing Fiber Optic | ||
2013 | Project: | PT. Unilever Walls | PT. Siemens Indonesia |
Service: | Maintenance of MV Panel | ||
2013 | Project: | PT WIKA PLTG Kaltim (Peaking) Project | Cooperation with PT. Graha Usaha Teknik |
Service: | Termination and Splicing of Fiber Optic Cable | ||
2013 | Project: | PT Satya Mitra Surya Perkasa | PT. Satya Mitra Surya Perkasa |
Service: | Design, Engineering, Installation & Testing Automatic Transfer Switch system for 6kV MV Switchgear | ||
2013 | Project: | PT Satya Mitra Surya Perkasa | PT. Satya Mitra Surya Perkasa |
Service: | Commissioning for setting Protection Relay Siemens Siprotec 7UT613 | ||
2013 | Project: | Kendal, Semarang - Jawa Tengah | CV. Sinar Kemulyaan |
Service: | Commissioning Electrical system | ||
2013 | Project: | MV Switchgear Simoprem SA4 for panbil, Batam | PT. Siemens Indonesia |
Service: | Commissioning LV MV Switchgear | ||
2013 | Project: | PT Kalbe Farma | PT. Siemens Indonesia |
Service: | Trouble shooting MV Panel at Kalbe Farma | ||
2013 | Project: | Turbine Maintenance for A luoi project in Vietnam | Voith Hydro Gmbh &Co.KG |
Service: | Turbine maintenance in Vietnam | ||
2013 | Project: | Engury Project in Georgia | Voith Hydro Gmbh &Co.KG |
Service: | Commissioning in Engury Project in Georgia | ||
2013 | Project: | Engury Project in Georgia | Voith Hydro Gmbh &Co.KG |
Service: | Generator Suprvision | ||
2013 | Project: | PT ULI | PT. Siemens Indonesia |
Service: | Preventive Maintenance of LV & MV Panel at skin plant | ||
2013 | Project: | ENGINEERING POSCO Merak | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning LV MV Switcgear and Transformer for Ash and Coal Handling | ||
2013 | Project: | PT ABB CFPP Merak | Cooperation with PT. Graha Usaha Teknik |
Service: | Commissioning 2 Line LV Switchgear | ||
2013 | Project: | EHMRW-TIMAS-CONOCO | PT. Siemens Indonesia |
Service: | Commissioning for setting Protection Relay Siemens | ||
2013 | Project: | PT Holcim, Narogong | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2013 | Project: | PT Indocement | PT. Siemens Indonesia |
Service: | Commissioning SIVACON LV Cubicle at Indocement | ||
2013 | Project: | PT ABB Indorama | Cooperation with PT. Graha Usaha Teknik |
Service: | Splicing and Testing of Fiber Optic | ||
2013 | Project: | KPC Project | PT. Siemens Indonesia |
Service: | Commissioning for setting Protection Relay Siemens | ||
2013 | Project: | 150kV GI CKL PS Phase VII Project | PT. Siemens Indonesia |
Service: | Grouting for HV Equipment Fondations | ||
2013 | Project: | Ratu Plaza | PT. Siemens Indonesia |
Service: | Installation Trafo & MV Switchgear | ||
2012 | Project: | PT Freeport Indonesia | PT. Siemens Indonesia |
Service: | Investigation of GIS 115kV-34OC-8000315.01 | ||
2012 | Project: | PT. Conoco | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2012 | Project: | PT. Unilever Indonesia, 7 Skin Project | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2012 | Project: | Antam Project | PT. Siemens Indonesia |
Service: | Electrical Service for Antam Project | ||
2012 | Project: | PT. Schulman Plastic Surabaya | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2012 | Project: | PT. Schulman Plastic Surabaya | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2012 | Project: | KNI Plant Bontang | PT. Siemens Indonesia |
Service: | Preventive maintenance | ||
2012 | Project: | Kaltim Prima Coal, Sangata Kalimantan Timur | PT. Siemens Indonesia |
Service: | Commissioning Medium Voltage Switch gear. | ||
2012 | Project: | Ratu Plaza Power System Upgrading, Jakarta | PT. Siemens Indonesia |
Service: | Dismantling, Installation and Commissioning Transformer and MV Switchgear equipment.and MV Switchgear equipment. | ||
2012 | Project: | Riau Andalan Pulp And paper, Riau | PT. Siemens Indonesia |
Service: | Maintenance MV Switchgear Siemens Simoprem | ||
2012 | Project: | PT. Kahatex Bandung | PT. Siemens Indonesia |
Service: | Installation and Commissioning for Automation system Upgrading. | ||
2012 | Project: | Unilever Plants Cikarang. | PT. Siemens Indonesia |
Service: | MV and LV distribution Preventive Maintenance | ||
2012 | Project: | Antam Project | PT. Siemens Indonesia |
Service: | Electrical Service for Antam Project | ||
2012 | Project: | PT. Schulman Plastic Surabaya | PT. Siemens Indonesia |
Service: | Commissioning Electrical system | ||
2012 | Project: | KNI Plant Bontang | PT. Siemens Indonesia |
Service: | Preventive maintenance | ||
2012 | Project: | Kaltim Prima Coal, Sangata Kalimantan Timur | PT. Siemens Indonesia |
Service: | Commissioning Medium Voltage Switchgear. | ||
2012 | Project: | Ratu Plaza Power System Upgrading, Jakarta | PT. Siemens Indonesia |
Service: | Dismantling, Installation and Commissioning Transformer and MV Switchgear equipment. | ||
2012 | Project: | Riau Andalan Pulp And paper, Riau | PT. Siemens Indonesia |
Service: | Maintenance MV Switchgear Siemens Simoprem | ||
2012 | Project: | PT. Kahatex Bandung | PT. Siemens Indonesia |
Service: | Installation and Commissioning for Automation system Upgrading. | ||
2012 | Project: | Unilever Plants Cikarang. | PT. Siemens Indonesia |
Service: | MV and LV distribution Preventive | ||
2012 | Project: | SementTonasa Cement Plant. | Cooperation with PT. Graha Usaha Teknik |
Service: | Fiber Optic Splicing and Testing for CCTV and SCADA System network. | ||
2012 | Project: | 500/150 KV Kesugihan Substation, Cilacap Jawa Tengah | PT. Siemens Indonesia |
Service: | Pre-Commissioning HV equipment and Protection Relay | ||
2012 | Project: | PT.Gunawan Dianjaya Steel, Steel factory rehabilitation | PT. Siemens Indonesia |
Service: | Commissioning Transformer, LV and MV Switchgear | ||
2012 | Project: | Indocement, Bogor | PT. Siemens Indonesia |
Service: | Installation and Commissioning Siemens Sivacon LV Switchgear. |